Solar Project
Execution planner for the Cultybraggan Solar PV Farm. Tracking 6 workstreams across feasibility, procurement, grid connection, ecology, planning, and funding.
20 tasks · 3 done · 8 in progress · Updated 2026-03-17
System Specification
300 kW
DC Capacity
Solar panels
200 kW
AC Inverter
Grid export cap
~500
Panels
720W each
TBC
Annual Yield
Estimated
750–1000
BESS (kWh)
Battery storage
50%
Electricity Target
Camp demand covered
£30,000
Community Fund
Per year (projected)
£253,965
Est. Cost
Ex-VAT
Project Phases
Feasibility
In ProgressOct 2025 → Mar 2026
Build-Out
Not StartedTBC → Oct 2027
Community Energy Security
Not StartedTBC → Mar 2029
Feasibility Progress
3 of 20 tasks complete15%
8 tasks in progress
Workstreams
Feasibility & Business Case
In ProgressKen Norton
1/4 tasks
Procurement & Costs
In ProgressKen Norton
1/4 tasks
Grid Connection & DNO
In ProgressJGM Construction
0/2 tasks
Ecology & Environment
In ProgressAndrea Loudon
1/3 tasks
Planning & Conservation
Not StartedFiona Blacke
0/4 tasks
Funding & Grants
In ProgressSeona Anderson
0/3 tasks