Solar Project

Execution planner for the Cultybraggan Solar PV Farm. Tracking 6 workstreams across feasibility, procurement, grid connection, ecology, planning, and funding.

20 tasks · 3 done · 8 in progress · Updated 2026-03-17

System Specification

300 kW
DC Capacity
Solar panels
200 kW
AC Inverter
Grid export cap
~500
Panels
720W each
TBC
Annual Yield
Estimated
750–1000
BESS (kWh)
Battery storage
50%
Electricity Target
Camp demand covered
£30,000
Community Fund
Per year (projected)
£253,965
Est. Cost
Ex-VAT

Project Phases

Feasibility

In Progress

Oct 2025 Mar 2026

Build-Out

Not Started

TBC Oct 2027

Community Energy Security

Not Started

TBC Mar 2029

Feasibility Progress

3 of 20 tasks complete15%

8 tasks in progress

Workstreams

Feasibility & Business Case

In Progress

Ken Norton

1/4 tasks

Procurement & Costs

In Progress

Ken Norton

1/4 tasks

Grid Connection & DNO

In Progress

JGM Construction

0/2 tasks

Ecology & Environment

In Progress

Andrea Loudon

1/3 tasks

Planning & Conservation

Not Started

Fiona Blacke

0/4 tasks

Funding & Grants

In Progress

Seona Anderson

0/3 tasks